Automatic Screen Stripping Machine
This specification is only applicable to the automatic screen reclaiming machine manufactured by our company.
Machine Workflow: Load screen → Spray rinsing & emulsion stripping → Compressed air air-knife drying → Unload screen
Manually place pending-reclaim screen into the washing chamber, set reclaiming duration, spray pressure and spray bar moving speed on touch screen then close front door. Press start button, the cleaning pump delivers reclaiming liquid from liquid tank to front & rear spray bars. Liquid sprays out in fan shape through nozzles to physically strip residual emulsion off screen surface. Waste liquid passes through multi-stage filtration including 500μm stainless steel filter → 200μm filter bag → 3~5μm filter bag before flowing into the recovery tank.
4-1 Machine Parametere
No. | Item | Specification | Remark |
1 | Max. Screen Size | L1200mm × W1300mm × T40mm | Maximum processing dimension |
2 | Solution Tank Volume | 80L + Recovery Tank 80L | - |
3 | Reclaiming Mode | Front & rear spray bars reciprocate left-right for spray washing | - |
4 | Drying Method | Compressed air blown from spray bars for drying | Remove residual water droplets |
5 | Filtration Structure | 500μm stainless steel filter(at bottom of washing chamber)+200μm filter bag+3~5μm filter bag | - |
6 | Reclaim & Cleaning Time | 2~3 min | - |
7 | Air Drying Time | 1~2 min | - |
8 | Cleaning Pump | AC380V, 3-phase,7.5KW high-pressure pump | 1 set |
9 | Spray Pressure | 1~20kg/cm² | - |
10 | Drive Motor | AC220V, 0.75KW servo motor | 1 set |
11 | Exhaust Port Dimension | Φ100mm × H30mm | - |
12 | Air Supply | 0.5~0.7Mpa, 800~1000L/min | - |
13 | Power Supply | AC380V,3-phase,50/60HZ,8.5KW | - |
14 | Overall Dimension | L2500mm×W1300mm×H1950mm | Original typo cm revised to mm |
15 | Net Weight | 750KG | - |
4-3 Technical Features
The TD-T2013 automatic screen reclaiming machine is customized to satisfy special emulsion stripping demands of screen printing frames with excellent compatibility as below:
5. Warranty & Domestic After-sales Service
(1)One-year warranty from the installation date under normal operating condition.
(2)Regular on-site inspection, technical exchange and field guidance.
(3)Free machine installation, operator training and lifelong free software upgrade.
(4)Free new cleaning process instruction and free training for newly recruited technicians.
(5)On-site service within 4~6 hours for Pearl River Delta, Yangtze River Delta, Chengdu-Chongqing regions; 24~48 hours for other domestic areas.
(6)Lifelong maintenance and continuous supply of original spare parts.